| Location: |
West-Central Colorado |
| Definition: |
Sum of the flows on the following transmission lines: |
|
Line:
|
Metered End:
|
| Hayden-Archer 230kV |
Archer |
| Craig-Ault 345kV |
Craig |
| Gore Pass-Blue River 230kV |
Blue River |
| Hayden-Gore Pass 138kV |
Gore Pass |
| Gore Pass 230/138kV Transformer |
Gore Pass 230 |
| Gunnison-Poncha 115kV |
Poncha |
| Poncha-Midway 230kV |
Midway/San Luis |
| Poncha-San Luis 230 kV |
San Luis |
| Basalt-Malta 230kV |
Basalt |
| Basalt-Hopkins 115kV |
Basalt |
| Rifle-Hopkins 230kV |
Rifle |
| Transfer Limit: |
West to East |
1675 MW |
| East to West |
Not defined |
| Critical Disturbance that limits the transfer capability: |
The critical disturbance is the outage of the Hayden-Gore
Pass 230 kV line and the remedial action of opening the parallel Hayden-Gore
Pass 138 kV line. The limiting elements are the overload of the Craig-Ault
345 kV and Rifle-Malta 230 kV lines. |
| When: |
Rating established in "Hayden-Blue River 230kV Transmission
Line Operating Study, Phase 1 Report - System Normal Operation" dated October
1987; and "Phase 2 Report - Line Outage Conditions" dated May 1988. The
operating study was conducted jointly by:
-
Colorado-Ute Electric Association (CUEA) [now PSCO and TSGT]
-
Platte River Power Authority (PRPA)
-
Public Service Company of Colorado (PSC)
-
Tri-State Generation and Transmission Cooperative (TSGT)
-
Western Area Power Administration (WAPA) - Salt Lake, Golden, Montrose,
Loveland
-
Salt River Project (SRP)
|
| System Conditions: |
This rating is independent of peak load/light load assumptions
or transfer levels between major areas of WSCC. This path is affected primarily
by power exchanges within Colorado, and historically the flows hav all
been west to east across the path. |
| Study Criteria: |
(Summary)
System intact:
-
Per unit voltages between 0.95 p.u. and 1.05 p.u.
-
All line and transformers loaded to less than continuous rating.
Single contingency outage conditions:
-
Per unit voltages between 0.90 p.u. and 1.10 p.u.
-
All lines loaded to less than 15 minute emergency ratings.
-
All transformers loaded to less than 30 minute emergency ratings.
-
Transient voltage swings down to 0.7 p.u. permitted
|
| Remedial Actions Required: |
Remedial actions are required to achieve the rated transfer
capability. Following an outage, all overloaded lines and transformers
must have their loadings reduced to continuous ratings within 15 minutes.
This is accomplished by reducing schedules, lowering local generation or
manually tripping a lower voltage parallel path for an outage of the Hayden-Gore
Pass 230kV line. |
| Formal Operating Procedure: |
There is a formal operating procedure, the most current
one dated April 10, 1997. WAPA-Rocky Mountain Region is the operating agent
and uses real-time flows to monitor the path. |
| Allocation: |
The transfer capability of the path is divided between
WAPA, PRPA, TSGT, and PSC. |
| Interaction w/Other Transfer Paths that would Reduce the Capability
of this path: |
None. |
| Contact Person: |
John Wetzel
Western Area Power Administration
Rocky Mountain Region
5555 East Crossroads Boulevard
Loveland, CO 80538-8986
(970) 490-7254
(970) 490-7213 - fax
wetzel@wapa.gov |