Transmission Tot 5 Header

 
This Path Rating (Tot Description) is provided for information only and is not to be considered as an official copy.  The official Path Ratings are maintained by the Western Systems Coordinating Council (WSCC) and can be requested from their web site at www.wscc.com.
 
 
Location: West-Central Colorado
Definition: Sum of the flows on the following transmission lines:
Line:
Metered End:
Hayden-Archer 230kV Archer
Craig-Ault 345kV Craig
Gore Pass-Blue River 230kV Blue River
Hayden-Gore Pass 138kV Gore Pass
Gore Pass 230/138kV Transformer Gore Pass 230
Gunnison-Poncha 115kV Poncha
Poncha-Midway 230kV Midway/San Luis
Poncha-San Luis 230 kV San Luis
Basalt-Malta 230kV Basalt
Basalt-Hopkins 115kV Basalt
Rifle-Hopkins 230kV Rifle
Transfer Limit: West to East 1675 MW
East to West Not defined
Critical Disturbance that limits the transfer capability: The critical disturbance is the outage of the Hayden-Gore Pass 230 kV line and the remedial action of opening the parallel Hayden-Gore Pass 138 kV line. The limiting elements are the overload of the Craig-Ault 345 kV and Rifle-Malta 230 kV lines. 
When: Rating established in "Hayden-Blue River 230kV Transmission Line Operating Study, Phase 1 Report - System Normal Operation" dated October 1987; and "Phase 2 Report - Line Outage Conditions" dated May 1988. The operating study was conducted jointly by: 
  • Colorado-Ute Electric Association (CUEA) [now PSCO and TSGT] 
  • Platte River Power Authority (PRPA) 
  • Public Service Company of Colorado (PSC) 
  • Tri-State Generation and Transmission Cooperative (TSGT) 
  • Western Area Power Administration (WAPA) - Salt Lake, Golden, Montrose, Loveland 
  • Salt River Project (SRP)
System Conditions: This rating is independent of peak load/light load assumptions or transfer levels between major areas of WSCC. This path is affected primarily by power exchanges within Colorado, and historically the flows hav all been west to east across the path.
Study Criteria: (Summary) 
System intact:
  • Per unit voltages between 0.95 p.u. and 1.05 p.u. 
  • All line and transformers loaded to less than continuous rating. 
Single contingency outage conditions:
  • Per unit voltages between 0.90 p.u. and 1.10 p.u. 
  • All lines loaded to less than 15 minute emergency ratings. 
  • All transformers loaded to less than 30 minute emergency ratings. 
  • Transient voltage swings down to 0.7 p.u. permitted
Remedial Actions Required: Remedial actions are required to achieve the rated transfer capability. Following an outage, all overloaded lines and transformers must have their loadings reduced to continuous ratings within 15 minutes. This is accomplished by reducing schedules, lowering local generation or manually tripping a lower voltage parallel path for an outage of the Hayden-Gore Pass 230kV line.
Formal Operating Procedure: There is a formal operating procedure, the most current one dated April 10, 1997. WAPA-Rocky Mountain Region is the operating agent and uses real-time flows to monitor the path.
Allocation: The transfer capability of the path is divided between WAPA, PRPA, TSGT, and PSC.
Interaction w/Other Transfer Paths that would Reduce the Capability of this path: None.
Contact Person:  John Wetzel
Western Area Power Administration
Rocky Mountain Region
5555 East Crossroads Boulevard
Loveland, CO 80538-8986
(970) 490-7254
(970) 490-7213 - fax
wetzel@wapa.gov

Transmission Area Map
RMA OASIS Home Page